Meydan Ardıçlı Construction Progress

 

Meydan Ardıçlı Construction Progress – 13.08.2018

1. E2-c Block 1st floor pavement manufacturing continues.
2. F2 Block 2nd basement floor pillar shear wall manufacturing continues.
3. A3 Block attic pavement manufacturing continues.
4. O3 Block 3rd basement floor pavement manufacturing continues.
5. E2-b Block 1st basement floor brick wall manufacturing continues.
6. E2-c Block 1st basement floor brick wall manufacturing continues.
7. B1 Block 1st Kat satin plaster manufacturing continues.
8. B1 Block façade jacketing manufacturing continues.
9. B1 Block side sustaining wall manufacturing continues.
10. Entrance formative pillar shear wall manufacturing continues.
11. D2 Block 3. Kat electrical piping manufacturing continues.
12. D2 Block 5. Kat electrical case panel manufacturing continues.
13. B1 Block fire cabinet assembly continues.