Meydan Ardıçlı Construction Progress

 

Meydan Ardıçlı Construction Progress – 01.12.2018

1. B7 Block foundation manufacturing is completed.
2. B7 Block 2. Basement Floor pavement manufacturing continues.
3. O7 Block foundation manufacturing is completed.
4. F2 Block 3. Floor pavement manufacturing continues.
5. O24 Block 2. Basement Floor pavement manufacturing continues.
6. Municipality leave area support wall manufacturing continues.
7. O1 Block pool parapet manufacturing continues.
8. B1 Block elevator assembly is completed.
9. B1 Block bathroom ceramic manufacturing continues.
10. B1 Block hallways and stairs ceiling paint manufacturing is completed.
11. B1 Block kitchen cabinet manufacturing started.
12. B1 Block fire exit assembly is completed.
13. B1 Block Attic pergola and ceramics manufacturing is completed.
14. B2 Block satin manufacturing continues.
15. B2 Block balcony windowledge manufacturing is completed.
16. B2 Block stair marble manufacturing is completed.
17. B2 Block wet area insulation manufacturing continues.
18. B2 Block elevator steel construction manufacturing is completed.
19. B3 Block leveling screed manufacturing continues.
20. B3-B4-B5 Blocks gypsum plaster manufacturing is completed.
21. B3-B4-B5 Blocks blind case manufacturing is completed.
22. B3 Block heating system inside apartments continues.
23. B3 Block façade rainfall piping manufacturing continues.
24. B1 Block natural gas harness manufacturing continues.
25. B1 Block radiator assembly manufacturing continues.
26. B1 Block switch plug assembly manufacturing continues.
27. B6 Block 4. Floor electric desanding manufacturing continues.
28. B6 Block 5. Floor electrical case panel manufacturing continues.
29. F1 Block foundation excavation manufacturing started.