Meydan Ardıçlı Construction Progress
Meydan Ardıçlı Construction Progress – 07.12.2019
- Stage car park cleaning and detail manufacturing continues.
- B3 block final cleaning work completed.
- B3 block balustrade manufacturing continues.
- B4 block final cleaning works in progress.
- B4 block parquet skirting has been completed.
- B5 block final coat paint manufacturing completed.
- B5 block parquet skirting production completed.
- B5 block railing continues to be manufactured.
- B6 block outer pocket
- he coat manufacturing continues.
- B7 block exterior cladding manufacturing continues.
- B9 Block 2. Basement floor column curtain manufacturing continues.
- B10 block basic manufacturing continues.
- F1 Block 4. Normal floor flooring manufacturing continues.
- Entrance jewelry stone veneer work continues.
- Stage steel entrance jewelry paint manufacturing completed.
- Stage parking Fire installation in progress.
- B3 block air conditioning installation completed.
- B5 block radiator installation continues.
- B5 block hand shower kit installation continues.
- B4 block intercom installation completed.
- B4 block fire button and flasher installation completed.
- B5 block spot Assembly completed.
- B5 block fire button and flasher installation complete.
- B5 block intercom Assembly in progress.
- Management Office electricity manufacturing completed.