Meydan Ardıçlı Construction Progress

 

     Meydan Ardıçlı Construction Progress – 07.12.2019

  • Stage car park cleaning and detail manufacturing continues.
  • B3 block final cleaning work completed.
  • B3 block balustrade manufacturing continues.
  • B4 block final cleaning works in progress.
  • B4 block parquet skirting has been completed.
  • B5 block final coat paint manufacturing completed.
  • B5 block parquet skirting production completed.
  • B5 block railing continues to be manufactured.
  • B6 block outer pocket
  • he coat manufacturing continues.
  • B7 block exterior cladding manufacturing continues.
  • B9 Block 2. Basement floor column curtain manufacturing continues.
  • B10 block basic manufacturing continues.
  • F1 Block 4. Normal floor flooring manufacturing continues.
  • Entrance jewelry stone veneer work continues.
  • Stage steel entrance jewelry paint manufacturing completed.
  • Stage parking Fire installation in progress.
  • B3 block air conditioning installation completed.
  • B5 block radiator installation continues.
  • B5 block hand shower kit installation continues.
  • B4 block intercom installation completed.
  • B4 block fire button and flasher installation completed.
  • B5 block spot Assembly completed.
  • B5 block fire button and flasher installation complete.
  • B5 block intercom Assembly in progress.
  • Management Office electricity manufacturing completed.