Meydan Ardıçlı Construction Progress

 

Meydan Ardıçlı Construction Progress – 05.08.2019

  • Stage 1 landscaping is completed.
  • Stage 1 pool construction continues.
  • Phase 1 insulation construction was completed.
  • Construction of partition wall between Stage 1 and Stage 2 continues.
  • 1st stage parking lot cleaning and detail works are continuing.
  • F1 Block 1 th floor construction continues.
  • B2 Block termination construction is in progress.
  • B2 Block door installation continues.
  • B3 Block kitchen bathroom cabinet installation continues.
  • B3 Block door installation continues.
  • B3 Block entrance hall construction is in progress.
  • B3 Block kitchen – bathroom counter installation continues.
  • B4 Block kitchen bathroom furniture installation continues.
  • B4 Block entrance door construction is in progress.
  • B4 Block elevator construction is in progress.
  • B5 Block entrance hall construction is in progress.
  • B5 Block kitchen bathroom furniture installation continues.
  • Construction of Paving Block B5 Block continues.
  • B5 Block elevator construction continues.
  • B6 Block exterior plaster and jacketing construction was completed 50%.
  • B7 Block exterior plaster and jacketing construction is continuing.
  • B8 Block wall construction continues.
  • Stage 1 water tank insulation construction was completed.
  • 1st stage parking lot fire installation continues.
  • Stage 1 landscape drainage piping continues.
  • 1st Stage landscaping irrigation installation continues.
  • 1st stage block supply clean water piping continues.
  • B5 Block collector installation is completed.
  • Bolard installation of 1st stage landscape lighting was completed.
  • Parking lot installation was completed.
  • B4 Block switch socket installation is completed.
  • B3 Block led strip installation continues.
  • Installation of the block entrances wallwasher continues.