Ncadde Ateş Corner Construction Progress

Ncadde Ateş Corner Construction Progress – 05.08.2019

 

     

      A BLOCK

  • 1st floor wall construction completed
  • 2nd floor wall construction was completed.
  • 3rd floor wall construction was completed.
  • Construction of the ground floor wall is in progress.
  • 1st basement floor wall construction was completed.
  • 2nd basement wall construction was completed.
  • Front and right side facade scaffolding installation is completed.
  • Front and right side facade black plaster production was completed.
  • The construction of the façade meshed plaster was completed.
  • The construction of the inner courtyard black plaster was completed.

B BLOCK

  • 1st floor wall construction was completed.
  • 2nd floor wall construction was completed.
  • 3rd floor wall construction was completed.
  • Construction of the ground floor wall is in progress.
  • 1st basement floor wall construction was completed.
  • Basement floor wall construction was completed.
  • Internal courtyard scaffolding installation was completed.
  • Right side facade scaffolding installation is in progress.
  • The construction of the right side wall mesh plaster was completed.
  • The construction of the inner courtyard black plaster was completed.

C BLOCK

  • 1st floor wall construction was completed.
  • 2nd floor wall construction was completed.
  • 3rd floor wall construction was completed.
  • 4th floor wall construction was completed.
  • Construction of the ground floor wall is in progress.
  • 1st basement floor wall construction was completed.
  • 2nd basement wall construction was completed.
  • The construction of the inner courtyard black plaster was completed.
  • Interior courtyard Eps floor construction is in progress.