NCadde Ottoman Construction Progress

NCadde Ottoman Construction Progress – 13.08.2018

• B Block ground floor pavement concrete manufacturing continues.
• B Block 3rd basement floor pillar iron reinforcement, mold and concrete manufacturing continues.

• A1 Block façade dark plaster manufacturing is completed.
• A2 Block façade dark plaster manufacturing is completed.
• Attic dark plaster manufacturing is completed.
• Commercial unit outer façade dark plaster manufacturing is completed.
• A1 – A2 Blocks brick – gas concrete wall manufacturing is completed.
• Attic brick wall manufacturing is completed.
• A Blocks basement floors gas concrete wall manufacturing is completed.
• A1 – A2 Blocks 1st, 2nd and 3rd normal floors electrical lines piping manufacturing inside apartments is completed.
• A1 – A2 Blocks 1st floor common area electrical case assembly manufacturing is completed.
• A Block 3rd basement (car park) floor al case assembly manufacturing is completed.
• A1 – A2 Block 1st normal floor electrical pipe manufacturing is completed. 2nd normal floor continues.
• A1 – A2 Blocks PPRC clean water line weld manufacturing is completed.
• A1 – A2 Blocks wet area PVC lower collection manufacturing continues.
• A1 – A2 Blocks 1st normal floor common area and inner apartment fire pipe welding manufacturing is completed. 2nd normal floor continues.
• Façade coating manufacturing continues.
• Commercial unit outer façade coating manufacturing continues.
• A2 Block attic insulation manufacturing is completed.
• A1 Block attic insulation manufacturing continues.
• Attic social facility wet area PPRC clean water line weld manufacturing is completed.
• A1 – A2 Blocks wet area geberit (built-in flush tank) assembly manufacturing is completed.