Ncadde Ottoman Construction Progress

NCadde Ottoman Weekly Construction Progress – 26.05.2018

• A2-A1 block patio insulation manufacturing continues.
• B block 2nd basement floor pillar shear wall reinforced concrete manufacturing continues.
• B block excavation is completed.
• A1 block facade dark plaster manufacturing is completed.
• A2 block facade dark plaster manufacturing is completed.
• A1 — A2 block brick-gas concrete wall manufacturing is completed.
• Attic brick wall manufacturing is completed.
• 2nd basement floor gas concrete wall manufacturing continues.
• Al – A2 blocks 1. normal floor electrical lines inside apartments piping manufacturing is completed. 2nd floor manufacturing is started.
• A1-A2 blocks 3rd normal floor pprc clean water line mechanical manufacturing is completed.
• Facade coating manufacturing continues.
• Attic insulation manufacturing continues.
• Attic dark plaster manufacturing is completed.