Ncadde Ottoman Construction Progress

NCadde Ottoman Construction Progress – 05.08.2019

  • B block 3rd basement concrete construction was completed.
  • Block B 2nd basement floor concrete construction was completed.
  • B block 1st basement concrete construction was completed.
  • B block ground floor concrete construction was completed.
  • Block B 1st normal floor table reinforced concrete construction continues.
  • B block 2nd normal floor curtain wall and column iron construction continues.
  • B block perimeter retaining concrete wall construction continues.
  • A block exterior carcass construction was completed.
  • A block brick-gas concrete wall construction was completed.
  • Construction of aerated concrete wall in A block basement was completed.
  • A block siding construction was completed.
  • A block commercial unit siding construction was completed.
  • A block 1,2 and roof terrace terrace construction was completed.
  • A block wet volume geberit (built-in reservoir) installation was completed.
  • A block basement floor is clean water piping installations were completed.
  • A block landscaping and landscape construction is completed.
  • Block A Ground, 1, 2 and 3. Normal floor common area heating and cooling pipe welding works are completed.
  • Block A 2nd floor indoor heating and cooling pipe welding works are continuing.
  • A block ground, 1st, 2nd and 3rd Normal floor common area and apartment fire pipe welding productions were completed.
  • A block sewage and rainwater sub-connection installations are completed.
  • A block pimapen joinery and glass assembly production was completed 85%.
  • Block 1, 2nd and 3rd normal floor apartment (sorti) wiring production was completed.
  • Block A, 1st, 2nd and 3rd floor in-circle weak current wiring production was completed.
  • Installation of block A, 1st, 2nd and 3rd floor circle column supply wiring is completed.
  • A block ground floor commercial unit supply wiring installation is completed.
  • A block 3 basement car park ceiling lighting installations were completed.
  • Block B 3rd basement car park ceiling lighting installations continue.
  • A block commercial unit natural gas piping installations were completed.
  • A block 1.2 and tower terrace slope screed concrete construction was completed.
  • Block A 3. basement car park fire spring installations were completed.
  • A block ground floor commercial unit ventilation duct installations were completed.