NLogo Construction Progress

NLogo Construction Progress – 13.08.2018

A Blocks are completed.
B3 Block electrical manufacturing continues.
B3 Block mechanical manufacturing continues.
B3 Block façade jacketing and paint manufacturing continues.
B3 Block gypsum plaster and wet place dark plaster manufacturing continues.
B3 Block leveling concrete finish manufacturing continues.
B2 Block brick wall manufacturing continues.
B2 Block coarse manufacturing is completed.
B2 Block façade catwalk assembly continues.
B2 Block front tower crane disassembly continues.
B1 Block 24th floor tunnel mold manufacturing continues.
C2 Block 1st floor manufacturing continues.
C1 Block ceiling floor manufacturing continues.
Open swimming pool is open for use.