Nlogo Construction Progress

NLogo Construction Progress – 20.01.2020

  • B3 block electricity production continues.
  • B3 block cabinet manufacturing continues.
  • B3 block mechanical manufacturing continues.
  • B3 block ceramic repairs are ongoing.
  • B3 block internal door manufacturing is finished.
  • Installation of B3 block fire doors continues.
  • B3 block passenger elevator steel manufacturing completed.
  • B3 block elevator installation continues.
  • B3 block parquet production is finished.
  • Paint production in B3 block apartment has been completed.(Corridor painting continues.)
  • B3 block steel door manufacturing completed.(The fire gate is in progress.)
  • B2 block wet place black plaster and plaster production continues.
  • B2 block electricity production continues.
  • B2 block mechanical manufacturing continues
  • B2 block plaster-plaster production 1. It continues on the floor.
  • B1 block scaffolding installation completed.
  • B1 block mantle continues.
  • C1 and C2 block Mezzanine was completed.
  • C2 Block 2.floor manufacturing continues.
  • C1 Block 1. Floor manufacturing started.
  • Bazaar vehicle crossing bridge fine manufacturing continues.