Nlogo Construction Progress

NLogo Construction Progress – 07.12.2019

  • B3 block electricity production continues.
  • B3 block cabinet manufacturing continues.
  • B3 block mechanical manufacturing continues.
  • B3 block ceramic repairs are ongoing.
  • B3 block internal door manufacturing is finished.
  • B3 block passenger elevator steel manufacturing completed.
  • B3 block elevator installation continues.
  • B3 block parquet production is finished.
  • B3 block steel door manufacturing completed.(The fire gate is in progress.)
  • B2 block wet place black plaster and plaster production continues.
  • B2 block electricity production continues.
  • B2 block mechanical manufacturing continues
  • B2 block plaster-plaster production 6. It continues on the floor.
  • B2 block exterior cladding manufacturing continues.
  • B1 block roof manufacturing continues.
  • B1 block scaffolding installation is in progress.
  • B1 block mantle continues.
  • C1 and C2 block Mezzanine was completed.
  • C2 Block 2.floor manufacturing continues.
  • Bazaar pedestrian bridge fine manufacturing continues.
  • O18 block manufacturing is completed.