Ödül Istanbul Construction Build

Ödül İstanbul weekly Construction Build – 13.08.2018

• G Block attic elevator tower manufacturing continues.
• C Block 36th floor pavement concrete is completed.
• D Block 36th floor pavement beam manufacturing started.
• F Block 39th floor shear wall manufacturing started.
• H Block 1st floor tunnel mold manufacturing continues.
• Op-06 foundation manufacturing started.
• G Block 6th floor brick manufacturing started.