Ödül İstanbul Construction Progress
Ödül İstanbul Construction Progress 07.12.2019
- B BlockFloor 1.soot tunnel concrete will be poured on 07.12.2019.
- E BlockFloor 2.soot tunnel concrete is being poured.
- F Block brick wall manufacturing continues.
- G Block shops brick wall manufacturing completed.
- G Block shops in front of the printing concrete manufacturing continues.
- G Block flat cable desant manufacturing continues.
- H Block flat cable desant manufacturing continues.
- H Block shops front floor leveling manufacturing is done.
- OP-07 Part 2.the basement floor floor concrete was poured.
- OP-10Basement floor flooring mold manufacturing continues.