Ödül İstanbul Construction Progress

Ödül İstanbul Construction Progress 07.12.2019

  • B BlockFloor 1.soot tunnel concrete will be poured on 07.12.2019.
  • E BlockFloor 2.soot tunnel concrete is being poured.
  • F Block brick wall manufacturing continues.
  • G Block shops brick wall manufacturing completed.
  • G Block shops in front of the printing concrete manufacturing continues.
  • G Block flat cable desant manufacturing continues.
  • H Block flat cable desant manufacturing continues.
  • H Block shops front floor leveling manufacturing is done.
  • OP-07 Part 2.the basement floor floor concrete was poured.
  • OP-10Basement floor flooring mold manufacturing continues.