Nlogo İnşaat Seyri

NLogo İnşaat Seyri – 03.11.2018

B3 Block electrical manufacturing continues.
B3 Block mechanical manufacturing continues.
B3 Block façade paint manufacturing is completed.
B3 Block leveling concrete finish manufacturing continues.
B3 Block façade catwalk disassembly continues.
B3 Block ceramic works continue.
B2 Block façade catwalk assembly continues.
B2 Block electrical manufacturing continues.
B2 Block mechanical manufacturing continues.
B2 Block façade jacketing manufacturing continues.
B1 Block brick wall manufacturing continues.
B1 Block 29th floor tunnel mold manufacturing is completed.
C1 and C2 Blocks ceiling floor manufacturing is completed.
Field print concrete works in lanscaping continues.